How Long Does It Typically Take to Renovate a Bathroom?
If updating the look of your home is on your list for this year, then you’ll likely wonder about how much time this type of project takes.
Here’s what you need to know when renovating your bathroom and what timelines to expect through the process.
Approximate Timeline for a Bathroom Renovation Project
It is important to remember that timelines are simply a guideline to know how long your bathroom renovation project should take.
The home’s age, the type of changes to be made, and contractor scheduling affect the competition times of bathroom renovation. But the most common time frame is around 24 days.
Demolition: 2 Days
Generally, the tear-out process for an existing bathroom takes around 2 days. Keep in mind that anything higher than ground level usually takes longer and older homes have a few more guidelines. As you might expect, a master suite will always be a bigger job than just a simple half bath.
Rough Carpentry: 2 Days
If your floors and walls are already in good shape, there’s a good chance you won’t even need this part of the renovation project. But if you’re expanding or you need a new subfloor, expect 2 additional days to your timeline.
Plumbing Rough-In: 1 to 2 Days
Basic plumbing and repiping should take under a day to finish. If you’re moving a toilet, tub, or shower, plan on using the full two days for changes.
Electrical Rough-In: 1 to 2 Days
Most electrical contractors can do this in under a day if the space is small and the existing wires and outlets don’t need much movement.
First Inspection: 1 Day
Inspections are a big part of any home renovation project. While the inspector’s actual time on the site is minimal, it could take a few days to schedule. Until they make an appearance and sign off on the project, work is pretty much at a standstill.
Insulation and Hang Drywall: 1 Day
Most bathroom renovations are small and require minimal insulation and drywall needs. Often, this can be completed in under a day.
Finish Drywall: 2 Days
The drywall finish process is a little more complicated. This is when your contractor applies joint compound, texture, and whatever else is necessary for a beautiful finish. Drying time and sanding are sometimes required, too.
Paint: 1 Day
When there are no fixtures or cabinets in the space, the painting process is super simple. Allow about a day for drying.
Final Inspection: 1 Day
The inspector will come out and make sure everything is up to standard. Like before, this could take a bit of time.
Tile Work: 2 Days
Your bathroom renovation starts to come together at this point. Your contractor will lay tiles on backsplashes or in a shower.
Depending on the area size, this could take up to 2 days. There also needs to be dry time and considerations for sealing grout.
Cabinetry and Trim: 1 Day
The cabinetry and trim process in most bathrooms is relatively simple. With a professional contractor in charge, expect this to take about a day.
Flooring: 2 Days
Floors are an important part of bathroom renovation. Vinyl flooring should take only a few hours. Tile or wood plank can take a few days to finish.
Fixtures and Hookups: 2 Days
Finally, there’s the process of installing fixtures, hooking up the toilet, and whatever else is necessary to finish the project.
Some contractors can wrap this up in about a day, while others take more time. Material delays can also prolong the process.
Other Tasks: 2 Days
Even on the easiest of bathroom projects, some things come up. Allocate a day or two to ensure your contractor addresses any additional details along the way.
Wrap Up: Hiring a Covington, LA Bathroom Renovation Contractor
At Northshore Renovations and Contracting, we love helping local property owners transform the look of their homes. If you live in Covington, Mandeville, Madisonville, or any surrounding community within Louisiana, we would love to hear from you. Contact us today for a no-obligation project quote.